Concrete calculator: cement, sand and aggregate

Enter the size of a slab, beam, column or footing and the grade of concrete. Get the cement bags, sand and aggregate it needs.

m
m
m

Result

Concrete volume
1.35 m³ (47.67 cft)
Cement
10.89 bags (544 kg)
Sand
0.57 m³ (20.02 cft)
Aggregate
1.13 m³ (40.05 cft)

Nominal mix by volume, dry volume = wet × 1.54, cement at 1440 kg/m³ and 50 kg per bag. Add wastage as per site practice.

Measuring a whole building? Upload the Revit model and Civiniq measures every element for you — free for 3 months.

Request access

The method

How it's calculated

  1. 1

    Wet volume

    Length × width × depth × number of elements.

  2. 2

    Dry volume

    Wet volume × 1.54. Dry materials shrink into a smaller volume once mixed with water, so more is needed.

  3. 3

    Split by the mix

    For M20 (1:1.5:3) the parts add up to 5.5: cement is 1/5.5, sand 1.5/5.5 and aggregate 3/5.5 of the dry volume.

  4. 4

    Cement in bags

    Cement volume × 1440 kg/m³ ÷ 50 kg per bag.

Worked example: 1 m³ of M20 concrete

  • Dry volume = 1 × 1.54 = 1.54 m³
  • Cement = 1.54 ÷ 5.5 = 0.28 m³ × 1440 = 403.2 kg = 8.06 bags
  • Sand = 1.54 × 1.5 ÷ 5.5 = 0.42 m³ (14.83 cft)
  • Aggregate = 1.54 × 3 ÷ 5.5 = 0.84 m³ (29.66 cft)

FAQ

Frequently asked questions

How many cement bags are needed for 1 cubic metre of M20 concrete?

About 8.06 bags (403 kg) for a nominal 1:1.5:3 mix, with 0.42 m³ of sand and 0.84 m³ of aggregate.

Why multiply by 1.54?

Dry cement, sand and aggregate fill the voids between each other when mixed with water, so the dry volume needed is about 54% more than the finished concrete.

Is this for design mix concrete?

No. It uses nominal mixes by volume. Design mixes (common for M25 and above) are proportioned by weight from a mix design and should use those quantities.

Should I add wastage?

Yes, usually 2–5% depending on site practice. The calculator shows the net quantity.