Skip to main content

Guide

How to calculate brickwork quantity: bricks, cement and sand

Step-by-step brickwork calculation: number of bricks, mortar, cement bags and sand for a wall, with a worked example for 1 m³ in CM 1:6 and the deductions to make.

By Civiniq Civil Estimation 6 min read

What you need to know first

Brickwork is measured by volume — cubic metres (m³) or cubic feet (cft) — for walls one brick thick or more. Half-brick walls (115 mm or 4½″) are usually measured by area instead. To estimate the materials you need four things: the wall's size, the brick size, the mortar ratio and the mortar joint thickness, normally 10 mm.

Brick typeSize without mortarSize with 10 mm jointBricks per m³
Modular190 × 90 × 90 mm200 × 100 × 100 mm500
Conventional230 × 110 × 70 mm240 × 120 × 80 mmabout 434

Step 1 — Work out the volume of brickwork

Multiply length × height × thickness for each wall, then take off the openings and the concrete that sits inside the wall.

  • Deduct door and window openings (by your measurement rules — IS 1200 doesn't deduct openings up to 0.1 m²).
  • Deduct lintels, beams and columns that run through the wall: that volume is concrete, not brickwork.
  • Measure each floor separately if your BOQ is floor by floor.

Step 2 — Count the bricks

Divide the brickwork volume by the volume of one brick including its mortar joints. For a modular brick that's 0.2 × 0.1 × 0.1 = 0.002 m³, so 1 m³ needs 500 bricks. Add 3–5% for breakage and cutting.

Step 3 — Find the mortar

The mortar is whatever isn't brick. Subtract the volume of the bricks themselves (without joints) from the wall volume to get the wet mortar. Dry materials take up more room than the finished mortar, so multiply by 1.33 to get the dry volume.

Step 4 — Split the mortar into cement and sand

For a 1:6 mix there are 7 parts in total: cement is 1/7 of the dry volume and sand 6/7. Convert cement to kilograms at 1440 kg/m³, then to 50 kg bags.

Worked example: 1 m³ of brickwork, modular bricks, CM 1:6

  • Bricks = 1 ÷ 0.002 = 500 nos (525 with 5% wastage)
  • Volume of bricks = 500 × (0.19 × 0.09 × 0.09) = 0.7695 m³
  • Wet mortar = 1 − 0.7695 = 0.2305 m³
  • Dry mortar = 0.2305 × 1.33 = 0.3066 m³
  • Cement = 0.3066 ÷ 7 = 0.0438 m³ × 1440 = 63.06 kg = 1.26 bags
  • Sand = 0.3066 × 6 ÷ 7 = 0.26 m³ (9.28 cft)

These are net quantities by the common site method. Rates and wastage vary by region — check against your own practice.

Doing it for a whole building

One wall is quick by hand. A whole building means hundreds of walls, every opening and lintel, floor by floor — that's where mistakes creep in. If the building is modelled in Revit, Civiniq reads every wall from the IFC model, deducts openings, lintels and beams from the 3D geometry, and prices the brickwork at your rates.

FAQ

Common questions

How many bricks are there in 1 cubic metre?

500 modular bricks (190 × 90 × 90 mm with 10 mm joints), or about 434 conventional bricks (230 × 110 × 70 mm).

How much cement is needed for 1 m³ of brickwork in 1:6?

About 1.26 bags (63 kg) of cement and 0.26 m³ of sand, with modular bricks.

Why multiply the mortar by 1.33?

Dry cement and sand shrink in volume once mixed with water, so about a third more dry material is needed than the volume of wet mortar.

Price your next model in minutes, not days.

Upload a Revit IFC and generate a priced BOQ with full measurement sheets. Free for 3 months — no credit card.