How to calculate brickwork quantity: bricks, cement and sand
Step-by-step brickwork calculation: number of bricks, mortar, cement bags and sand for a wall, with a worked example for 1 m³ in CM 1:6 and the deductions to make.
By Civiniq Civil Estimation 6 min read
What you need to know first
Brickwork is measured by volume — cubic metres (m³) or cubic feet (cft) — for walls one brick thick or more. Half-brick walls (115 mm or 4½″) are usually measured by area instead. To estimate the materials you need four things: the wall's size, the brick size, the mortar ratio and the mortar joint thickness, normally 10 mm.
| Brick type | Size without mortar | Size with 10 mm joint | Bricks per m³ |
|---|---|---|---|
| Modular | 190 × 90 × 90 mm | 200 × 100 × 100 mm | 500 |
| Conventional | 230 × 110 × 70 mm | 240 × 120 × 80 mm | about 434 |
Step 1 — Work out the volume of brickwork
Multiply length × height × thickness for each wall, then take off the openings and the concrete that sits inside the wall.
- Deduct door and window openings (by your measurement rules — IS 1200 doesn't deduct openings up to 0.1 m²).
- Deduct lintels, beams and columns that run through the wall: that volume is concrete, not brickwork.
- Measure each floor separately if your BOQ is floor by floor.
Step 2 — Count the bricks
Divide the brickwork volume by the volume of one brick including its mortar joints. For a modular brick that's 0.2 × 0.1 × 0.1 = 0.002 m³, so 1 m³ needs 500 bricks. Add 3–5% for breakage and cutting.
Step 3 — Find the mortar
The mortar is whatever isn't brick. Subtract the volume of the bricks themselves (without joints) from the wall volume to get the wet mortar. Dry materials take up more room than the finished mortar, so multiply by 1.33 to get the dry volume.
Step 4 — Split the mortar into cement and sand
For a 1:6 mix there are 7 parts in total: cement is 1/7 of the dry volume and sand 6/7. Convert cement to kilograms at 1440 kg/m³, then to 50 kg bags.
Worked example: 1 m³ of brickwork, modular bricks, CM 1:6
- Bricks = 1 ÷ 0.002 = 500 nos (525 with 5% wastage)
- Volume of bricks = 500 × (0.19 × 0.09 × 0.09) = 0.7695 m³
- Wet mortar = 1 − 0.7695 = 0.2305 m³
- Dry mortar = 0.2305 × 1.33 = 0.3066 m³
- Cement = 0.3066 ÷ 7 = 0.0438 m³ × 1440 = 63.06 kg = 1.26 bags
- Sand = 0.3066 × 6 ÷ 7 = 0.26 m³ (9.28 cft)
These are net quantities by the common site method. Rates and wastage vary by region — check against your own practice.
Doing it for a whole building
One wall is quick by hand. A whole building means hundreds of walls, every opening and lintel, floor by floor — that's where mistakes creep in. If the building is modelled in Revit, Civiniq reads every wall from the IFC model, deducts openings, lintels and beams from the 3D geometry, and prices the brickwork at your rates.